Quantitative Aptitude | Questions

Time and Work questions with solutions

Time and Work is a Quantitative Aptitude topic for competitive exams. It is tested in RBI Office Attendant, Punjab Police Constable, RRB Ministerial and Isolated Categories, RPF SI and other exams. This page has 35 solved time and work questions written to the official pattern, with a worked solution under each.

35 questionsQuantitative Aptitude
  1. Question 1Easy

    8 workers finish a task in 10 days. How many days will 5 workers take at the same rate?

    • A.10
    • B.18
    • C.22
    • D.16Correct
    • E.14
    Show solution

    The work is 10×8 = 80 worker-days, so 5 workers take 80/5 = 16 days.

  2. Question 2Easy

    12 workers finish a task in 18 days. How many days will 6 workers take at the same rate?

    • A.38
    • B.36Correct
    • C.50
    • D.22
    • E.34
    Show solution

    The work is 18×12 = 216 worker-days, so 6 workers take 216/6 = 36 days.

  3. Question 3Easy

    12 men can complete a work in 15 days. How many days will 20 men take to do the same work?

    • A.9Correct
    • B.12
    • C.8
    • D.10
    Show solution

    The work is 12 × 15 = 180 man-days. With 20 men it takes 180 ÷ 20 = 9 days.

  4. Question 4Easy

    8 workers finish a task in 24 days. How many days will 4 workers take at the same rate?

    • A.48Correct
    • B.32
    • C.64
    • D.50
    • E.46
    Show solution

    The work is 24×8 = 192 worker-days, so 4 workers take 192/4 = 48 days.

  5. Question 5Moderate

    If 6 workers finish a job in 8 days, how many days will 4 workers take (same efficiency)?

    • A.12 daysCorrect
    • B.10 days
    • C.16 days
    • D.9 days
    Show solution

    Total work = 6 × 8 = 48 worker-days. With 4 workers: 48/4 = 12 days.

  6. Question 6Moderate

    12 workers finish a task in 10 days. How many days will 8 workers take at the same rate?

    • A.10
    • B.15Correct
    • C.20
    • D.21
    • E.9
    Show solution

    The work is 10×12 = 120 worker-days, so 8 workers take 120/8 = 15 days.

  7. Question 7Moderate

    9 workers finish a task in 20 days. How many days will 10 workers take at the same rate?

    • A.23
    • B.18Correct
    • C.26
    • D.13
    • E.10
    Show solution

    The work is 20×9 = 180 worker-days, so 10 workers take 180/10 = 18 days.

  8. Question 8Moderate

    4 workers complete a job in 12 days. How many days will 6 workers take at the same rate?

    • A.8Correct
    • B.18
    • C.6
    • D.9
    Show solution

    Total work = 4 × 12 = 48 worker-days. With 6 workers, time = 48/6 = 8 days.

  9. Question 9Moderate

    A can do a piece of work in 12 days and B in 6 days. Working together, in how many days will they finish it?

    • A.4Correct
    • B.5
    • C.3
    • D.6
    Show solution

    In one day A does 1/12 and B does 1/6 = 2/12, together 3/12 = 1/4 of the work, so they finish in 4 days.

  10. Question 10Moderate

    A and B can complete a task in 12 days and 18 days respectively. Working together, in how many days will they finish it?

    • A.7.2 daysCorrect
    • B.15 days
    • C.6 days
    • D.9 days
    Show solution

    Combined rate = 1/12 + 1/18 = 5/36 of the task per day. Time = 36/5 = 7.2 days.

  11. Question 11Moderate

    A can finish a task in 10 days and B in 15 days. Working together, how many days will they take?

    • A.6Correct
    • B.5
    • C.8
    • D.12
    Show solution

    A's rate = 1/10 per day, B's rate = 1/15 per day. Combined rate = 1/10 + 1/15 = 5/30 = 1/6. So together they finish in 6 days.

  12. Question 12Moderate

    A can complete a reinsurance report in 12 days and B in 18 days. Working together, in how many days will they finish?

    • A.7.2 daysCorrect
    • B.15 days
    • C.6 days
    • D.8 days
    Show solution

    Combined rate = 1/12 + 1/18 = 5/36 of the work per day. Time = 36/5 = 7.2 days.

These are 12 of 35 time and work questions in the bank. Attempt the rest with instant feedback in the practice drills, or under a clock in the mock tests.

Frequently asked questions

How many Time and Work questions are here?

This page shows 12 worked time and work questions from a bank of 35, spanning 4 easy, 23 moderate and 8 hard. The full set is available to attempt in the timed-free practice drills and the mock tests.

Which exams ask Time and Work questions?

Time and Work is part of the Quantitative Aptitude syllabus for RBI Office Attendant, Punjab Police Constable, RRB Ministerial and Isolated Categories, RPF SI, RRB Section Controller, RPF Constable, RRB JE, RRB Technician, RRB ALP, RRB Group D, RRB NTPC, NABARD Office Attendant. Weightage varies by exam and stage — check each exam's page for its pattern.

Are these Time and Work questions free, and are the answers reliable?

Yes. Every question is free, written in-house to the exam pattern rather than copied from a real paper, and the numeric answer keys are recomputed independently at build time — a wrong key fails the build rather than reaching you.